It therefore makes sense (to the beancounters) if they are slipping a bit, to concentrate on an easy area, and defer the tricky ones that they had planned to do.

A lot of missed targets are also down to third parties.

* Councils taking a long time to approve planning.

* Councils refusing planning permission.

* Local electricity network operator taking a long time to provide power to cabinet (very common reason).

and another common one BT has to deal with:

* Local ducting in worse condition than expected.

This can be a double whammy. First because it delays getting the fibre to the cabinet and secondly because clearing it requires roadworks which come with their own delays and problems.