Reminds me of
The time that a datacenter at a site I was consulting had to undergo some minor reorganization to account for growth in its SAP environment (I was a storage consultant on that project) The problem was that the servers (across 7 or 8 racks IIRC) that needed to be moved were running some super important homegrown application and among the most important the company had, with almost no tolerance for downtime. Worse, these were not clustered so you couldn't simply shut down a server, move it, then power it up. The business owners of that system were throwing out dates months away when their systems could be relocated. Plus to avoid this situation ever again, the business owners of the systems to be moved wanted them placed in the newly opened section of the datacenter, which was a LONG way (easily over two hundred meters) from the current location. They had a DR site but actually activating it would apparently cost a ton of money, and the CIO vetoed any plan involving use of DR to accomplish the move (probably they just weren't confident it would actually work)
The possibility of waiting months until the new servers could be installed was a big problem for the SAP project (maybe not for me, if I was able to stick around and keep billing while we waited) so the leader of that project asked to send a few of his people to their meetings to figure out a better plan. Before the meeting we went out onto the floor to inspect the systems, and it looked like while they weren't clustered, as such, they were fitted out with redundancy for power, network and fibre channel.
So a plan was hatched to move the racks with these extremely important servers while they were running. It was determined that if network and fibre channel cables were extended from its new home to its current home, one set of network cables and one set of FC cables could be disconnected, and these new extended connectors substituted, then the other set disconnected, and the redundant set of long connectors substituted, so it was running on the extensions with redundancy (in case of a mishap, like a rack wheel running over a fiber cable lol) To handle ethernet distance limitations ethernet switches were laid on top of the rack to be moved, on a table next to the spot where the rack would be moved to, and ethernet cables carefully measured as being 99 meters long were prepared. There were a couple intermediate switches along the path as well (since ethernet is limited to 100 meters) powered by an unplugged UPS. Then a rack could VERY carefully be moved, with people gathering up the slack in those ever so important overly long cables (as well as the intermediate switches and UPSes) until it reached its new home where it would be connected to first one, then another set of normal length cables.
The one hitch was power, the electricians were wholly against the idea of powering everything with very long power cables with multiple extensions because they didn't know what the effect of voltage loss across such a long run would be and it was way out of spec for anything they had ever done before. There were some options discussed about plugging and unplugging it along the way with shorter cables, but the solution ended up being a pair of rather beefy UPSes that would follow along on a cart behind it so the rack would run on battery providing redundant power.
This was rehearsed several times with racks containing test/QA servers from that project being shuttled back and forth multiple times until the business owners were satisfied this crazy plan would work. I actually stayed that weekend even though I wasn't part of the actual move, as did a few of the other SAP consultants, because we just had to watch something we spent a couple long weeks planning actually work. And it did, without a single hitch. Well, other than when one of the racks was moved one of the switches haphazardly laying on top shifted off (possibly because the person gathering the ethernet cable slack was a bit too aggressive) and almost took out one of the guys pushing the rack. But despite crashing to the floor and gaining a rather nasty looking dent in one corner, the switch kept functioning.
Since the guys doing this move were all regular employees and their business owners were nowhere to be seen, us consultants took them all out afterwards (bars open until 4am on Saturday came in handy) boy did they get wasted. They had been under a lot of stress with so much worry about the move, but they pulled it off perfectly!